Change of plan to weekend roadworks at Testo's as progress continues on A19 flyover

Plans for a full closure on the A19 this weekend have changed to a lane closure as work continues on the huge multi-million pound transformation of Testo’s Roundabout.
Watch more of our videos on Shots! 
and live on Freeview channel 276
Visit Shots! now

While a full closure will still take place tonight, Friday, December 4, from 8pm, on the northbound A19 from North Hylton to Testo’s, the A184 westbound Testo’s to West Pastures, and the north and south sides of Testo’s roundabout, it now says it will remove the full closure at 6am tomorrow.

Read More
Drone images show how work is progressing on new A19 mega bridge at Testo's
A drone image taken by Highways England as work is carried out at Testo's Roundabout.A drone image taken by Highways England as work is carried out at Testo's Roundabout.
A drone image taken by Highways England as work is carried out at Testo's Roundabout.
Hide Ad
Hide Ad

It will be replaced with a lane closure, which will allow A19 traffic to head north to South Shields and beyond or west along the A184 to Gateshead.

The north and south side of Testo’s roundabout will be closed until 6am on Monday, however if work finishes sooner the section will be reopened early.

Further restrictions are planned for next weekend, with the project scheduled for completion next summer.

It will see the westbound A184 White Mare Pool to Testo’s closed, along with the northbound Testo’s to Boldon.

The site compound which is being used for the Testo's roundabout schemeThe site compound which is being used for the Testo's roundabout scheme
The site compound which is being used for the Testo's roundabout scheme
Hide Ad
Hide Ad

The £124.5 million upgrade project is being overseen by Highways England project manager Liam Quirk, who said: “We’re making good progress and this weekend we’re starting the final stages of laying the new road surface on the south west corner of the roundabout.

"The following weekend we are aiming to complete the connection from the north side of the roundabout onto the new slip roads.

“We appreciate that drivers will be using the roads in the run-up to Christmas and we aim to cause as little disruption as possible.

"We are trying to complete the work as early as we can for road users, who have been patient throughout the scheme.”

Hide Ad
Hide Ad

More information on the project can be found on Twitter via @highwaysNEAST or visit highwaysengland.co.uk/our-work/yorkshire-and-north-east/a19-testo-s-junction/.

You can subscribe to this website and enjoy unlimited access to local news, information and puzzles online.

With a digital subscription, you can read more than 5 articles, see fewer ads, enjoy faster load times, and get access to exclusive newsletters and content.

Simply click ‘Subscribe’ in the menu.