Change of plan to weekend roadworks at Testo's as progress continues on A19 flyover
and on Freeview 262 or Freely 565
While a full closure will still take place tonight, Friday, December 4, from 8pm, on the northbound A19 from North Hylton to Testo’s, the A184 westbound Testo’s to West Pastures, and the north and south sides of Testo’s roundabout, it now says it will remove the full closure at 6am tomorrow.
Advertisement
Hide AdAdvertisement
Hide AdIt will be replaced with a lane closure, which will allow A19 traffic to head north to South Shields and beyond or west along the A184 to Gateshead.
The north and south side of Testo’s roundabout will be closed until 6am on Monday, however if work finishes sooner the section will be reopened early.
Further restrictions are planned for next weekend, with the project scheduled for completion next summer.
It will see the westbound A184 White Mare Pool to Testo’s closed, along with the northbound Testo’s to Boldon.
Advertisement
Hide AdAdvertisement
Hide AdThe £124.5 million upgrade project is being overseen by Highways England project manager Liam Quirk, who said: “We’re making good progress and this weekend we’re starting the final stages of laying the new road surface on the south west corner of the roundabout.
"The following weekend we are aiming to complete the connection from the north side of the roundabout onto the new slip roads.
“We appreciate that drivers will be using the roads in the run-up to Christmas and we aim to cause as little disruption as possible.
"We are trying to complete the work as early as we can for road users, who have been patient throughout the scheme.”
Advertisement
Hide AdAdvertisement
Hide AdMore information on the project can be found on Twitter via @highwaysNEAST or visit highwaysengland.co.uk/our-work/yorkshire-and-north-east/a19-testo-s-junction/.