See the latest development as New Wear Crossing passes latest milestone

Sunderland's New Wear Crossing has passed its latest milestone, with all its supporting cables now in place.

Structural engineering company VSL International has completed the final installation of the 28 cable stays, and tensioned the cables to 50 percent of their intended load, as work continues to finish the new bridge by the spring.

The New Wear Crossing dominates the landscape

The New Wear Crossing dominates the landscape

The next stage of tensioning - also known as stressing - will take place next month, when the cable tension will be brought up to the full design load, allowing the team to adjust and tension them just enough to lift the bridge deck off the blue steel temporary supports that were constructed in the river to take the weight of the structure.

The temporary supports will be gradually removed over the coming months, leaving only the pylon and the bridge deck on display in the river.

Finishing works, such as road surfacing, paving, lighting, the installation of railings and carrying out road markings, must all be complete before the cable stays can be finely adjusted and locked off at the end of construction.

Stephen McCaffrey, Project Director for Farrans Construction and Victor Buyck Steel Construction, which formed a joint venture to deliver the project on behalf of Sunderland City Council, said he was pleased with progress: "The installation of the cable stays has been a major, complex task, but it has gone to plan and on programme,” said Stephen.

All the New Wear Crossing's cable stays are now in place

All the New Wear Crossing's cable stays are now in place

"The cables have brought the bridge to life and enabled everyone to appreciate just how impressive it’s going to be and the impact it will have in the years to come.

"People could be forgiven for thinking the bridge is very close to opening as the structure looks complete from a distance. However, the reality is that we still have quite a lot to do, such as completing the road works on both sides of the river, getting the surface of the bridge deck finished and all of those additional works and safety features complete."

Work began on the New Wear Crossing – Sunderland’s first bridge across the River Wear in more than 40 years – in May 2015.

It is Phase 2 of the Sunderland Strategic Transport Corridor, which aims to improve links between the A19 and Sunderland City Centre and the Port of Sunderland. The new bridge will also open up land for regeneration along the south side of the river, help to create jobs, and reduce congestion around the city.

Tensioning the cable stays

Tensioning the cable stays

During the first 18 months, much of the work centred around clearing the site in Pallion and Castletown, building the foundations, and fabricating and assembling the steel pylon and bridge deck.

However, this year, the bridge has become much more visible, with the 105m pylon being erected in February, the bridge deck launched across the river in spring, and the installation of the cable stays during the summer.

Sunderland City Council Leader Coun Paul Watson, said: "The installation of the cable stays is a pivotal part of the construction of the new bridge because it means much of the temporary works that were built to support it can now be removed and we can start to appreciate just how impressive the New Wear Crossing is.

"Already, we can see that it’s going to be a beautiful addition to the Sunderland skyline and one that will have a profound impact on the city.

A stunning view of the New Wear Crossing with all the cable stays in place

A stunning view of the New Wear Crossing with all the cable stays in place

"There is no doubt that this bridge will signal change in Sunderland; change for the better. It will lead to regeneration along the southbank of the river, help to bring new jobs and investment, and show that our ambitions are great. It will show that Sunderland is very much open for business."

Cable stay specialists and operatives from VSL International  installing the cable stays between the pylon and the bridge deck

Cable stay specialists and operatives from VSL International installing the cable stays between the pylon and the bridge deck

An aerial view of the bridge

An aerial view of the bridge

The New Wear Crossing is taking shape

The New Wear Crossing is taking shape